BRAINTREE- SAFE ROUTES TO SCHOOL (ROSS ELEMENTARY SCHOOL)
As part of the SRTS Program, Town has been selected for sidewalk improvements for the Ross School. Sidewalks are to be constructed along Burroughs Road and Perry Street. Reconstruction of ADA wheelchair ramps. Installation of pedestrian countdown signal.
Location:
  • Town of Braintree
  • Resident Engineer: Anthony Lourenco
    Construction Contract Value: $1,196,725.00
    Construction Bid Price: $567,115.00
    Initial Construction Estimate: $605,595.00
    District: District 6

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84361 -- Construction Contract
    Sidewalk Improvements on Sections of Burroughs and Perry Roads and Commercial, Elm and Hayward Streets (Safe Routes to School Ross Elementary School) (Re-advertised Project). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/02/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/20/2011
    Project Initiation Form PIF Entered 07/20/2011
    Project Initiation Form PRC Submitted 07/20/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 07/13/2013
    Project Status Advertised 08/16/2014
    Project Management
    100% Design 100% Package Received 12/21/2012
    100% Design 100% Package Comments to DE 03/11/2013
    25% Design 25% Package Received 05/14/2012
    25% Design Design Public Hearing 11/28/2012
    75% Design 75% Package Received 05/15/2012
    75% Design 75% Package Comments to DE 12/17/2012
    Final Design PS&E Received 04/17/2013
    Final Design PS&E to FAPRO 07/09/2013
    Final Design PS&E to FAPRO 08/13/2014