Project Description:
ANDOVER- LAWRENCE- BRIDGE REHABILITATION, A-09-036, I-495 OVER ST 28 (SB), A-09-037, I-495 OVER B&M AND MBTA, A-09-041, I-495 OVER ST 28 (NB)
The existing 3-span simply supported superstructures will be replaced with continuous superstructures to eliminate the deck joints. The structure will be widened to accommodate a future added lane and increase shoulder width to current standards.
Location:
  • Town of Andover
  • City of Lawrence
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2023
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $161,302,508.20
    Estimated Total Federal Participating Construction Cost: $166,453,746.43
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/11/2023 )

    Contracts (3) Progress
    # 58996 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: ANDOVER
    LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Funding removed via STIP Action 5.
  • No funding records for this TIP line

    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: ANDOVER
    LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Funding removed via STIP Action 5.
  • No funding records for this TIP line

    Planned Federal FY: 2026
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: ANDOVER
    LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Funding removed via STIP Action 5.
  • No funding records for this TIP line

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/21/2011
    Project Initiation Form PIF Entered 08/04/2011
    Project Initiation Form PRC Submitted 08/04/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 02/11/2023
    Project Management
    100% Design 100% Package Received 01/27/2023
    25% Design 25% Package Received 05/10/2017
    25% Design Design Public Hearing 11/17/2021
    Final Design PS&E to FAPRO 01/27/2023