Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ANDOVER- LAWRENCE- BRIDGE REHABILITATION, A-09-036, I-495 OVER ST 28 (SB), A-09-037, I-495 OVER B&M AND MBTA, A-09-041, I-495 OVER ST 28 (NB)
The existing 3-span simply supported superstructures will be replaced with continuous superstructures to eliminate the deck joints. The structure will be widened to accommodate a future added lane and increase shoulder width to current standards.
Location:
  • Town of Andover
  • City of Lawrence
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2023
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $161,302,508.20
    Estimated Total Federal Participating Construction Cost: $166,453,746.43
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/11/2023 )

    Contracts (3) Progress
    # 58996 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/21/2011
    Project Initiation Form PIF Entered 08/04/2011
    Project Initiation Form PRC Submitted 08/04/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 02/11/2023
    Project Management
    100% Design 100% Package Received 01/27/2023
    25% Design 25% Package Received 05/10/2017
    25% Design Design Public Hearing 11/17/2021
    Final Design PS&E to FAPRO 01/27/2023