| Project Description: |
ANDOVER- LAWRENCE- BRIDGE REHABILITATION, A-09-036, I-495 OVER ST 28 (SB), A-09-037, I-495 OVER B&M AND MBTA, A-09-041, I-495 OVER ST 28 (NB)
The existing 3-span simply supported superstructures will be replaced with continuous superstructures to eliminate the deck joints. The structure will be widened to accommodate a future added lane and increase shoulder width to current standards.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2023 |
| Project Manager: | Robert P Antico![]() |
| Estimated Total Contract Cost: | $161,302,508.20 |
| Estimated Total Federal Participating Construction Cost: | $166,453,746.43 |
| District: | District 4 |
| Current Status: | This project has been advertised for construction bids. (as of 02/11/2023 ) |
|