Planned Federal FY: |
2023 |
Responsible MPO: |
Merrimack Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
ANDOVER
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Project ACd over 2023-2026
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$68,092,348.00 |
State Cost: |
$17,023,087.00 |
Total Cost: |
$85,115,435.00 |
|
|
|
Planned Federal FY: |
2024 |
Responsible MPO: |
Merrimack Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
ANDOVER
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Project ACd over 2023-2026
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$48,000,000.00 |
State Cost: |
$12,000,000.00 |
Total Cost: |
$60,000,000.00 |
|
|
|
Planned Federal FY: |
2025 |
Responsible MPO: |
Merrimack Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
ANDOVER
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Project ACd over 2023-2026
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$9,860,780.80 |
State Cost: |
$2,465,195.20 |
Total Cost: |
$12,325,976.00 |
|
|
|
Planned Federal FY: |
2026 |
Responsible MPO: |
Merrimack Valley Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
ANDOVER
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
Project ACd over 2023-2026
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$12,506,871.20 |
State Cost: |
$3,126,717.80 |
Total Cost: |
$15,633,589.00 |
|
|
|
|