Project Description:
SOMERVILLE- BRIDGE PRESERVATION, S-17-031, I-93 NB AND SB FROM ROUTE 28 TO TEMPLE STREET
The project scope will include replacement of the northbound and southbound viaduct expansion joints including ramps; replacement of northbound and southbound median and outside fascia barriers.
Location:
  • City of Somerville
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Cooper Martens
    Construction Bid Price: $33,962,794.00
    District: District 4
    Current Status: Construction activities continue to progress from north to south along the length of the viaduct. Activities include concrete pier demolition/repairs and diaphragm demolition. This work will continue until the end of February, and start up again in the Spring of 2024. (as of 02/06/2024)

    Contracts (3) Progress
    # 115835 -- Construction Contract
    Bridge Rehabilitation and Related Work Br. No. S-17-031 (Including Ramps) on a Section of Interstate 93 37% Complete
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/15/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Construction activities continue to progress from north to south along the length of the viaduct. Activities include concrete pier demolition/repairs and diaphragm demolition. This work will continue until the end of February, and start up again in the Spring of 2024.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/01/2011
    Project Initiation Form PIF Entered 08/05/2011
    Project Initiation Form PRC Submitted 08/05/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 08/07/2021
    Project Management
    100% Design 100% Package Received 04/15/2021
    100% Design 100% Package Received 07/01/2021
    25% Design 25% Package Received 11/25/2020
    75% Design 75% Package Received 11/25/2020
    75% Design 75% Package Comments to DE 01/04/2021
    75% Design 75% Plans Approved 03/05/2021
    Final Design PS&E Received 07/01/2021
    Final Design PS&E Received - Resub 1 07/20/2021