Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOMERVILLE- BRIDGE PRESERVATION, S-17-031, I-93 NB AND SB FROM ROUTE 28 TO TEMPLE STREET
Location:
  • City of Somerville
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Joseph Stasio
    Construction Bid Price: $33,962,794.00
    District: District 4
    Current Status: Substructure concrete excavation, reinforcement repair, and concrete placement for column repairs continues within the fenced-in area on the north side of the viaduct (Piers 2-8). Beam end shoring installation and repairs to the concrete caps are scheduled to begin in September. Steel repairs and painting work on the superstructure will commence shortly thereafter. Nighttime work on I-93 is planned for late Summer/early Fall of 2022. Real Time Traffic Management (RTTM) will be implemented prior to work on I-93. (as of 08/16/2022)

    Contracts (3) Progress
    # 115835 -- Construction Contract
    Bridge Rehabilitation and Related Work Br. No. S-17-031 (Including Ramps) on a Section of Interstate 93 4% Complete
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/15/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/01/2011
    Project Initiation Form PIF Entered 08/05/2011
    Project Initiation Form PRC Submitted 08/05/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 08/07/2021
    Project Management
    100% Design 100% Package Received 04/15/2021
    100% Design 100% Package Received 07/01/2021
    25% Design 25% Package Received 11/25/2020
    75% Design 75% Package Received 11/25/2020
    75% Design 75% Package Comments to DE 01/04/2021
    75% Design 75% Plans Approved 03/05/2021
    Final Design PS&E Received 07/01/2021
    Final Design PS&E Received - Resub 1 07/20/2021