BOSTON- MEDIAN REPAIR ON I-90, FROM COMMONWEALTH AVENUE TO DALTON STREET (APPROX. 1.5 MILES), INCLUDES SUBSTRUCTURE IMPROVEMENTS TO B-16-005, COMM AVE. OVER I-90
The project involves median repair along I-90 for approximately 1.5 miles, from Commonwealth Avenue to Dalton Street. Ir also includes substructure improvements to the Commonwealth Avenue bridge over the Massachusetts Turnpike and MBTA.
Location:
  • City of Boston
  • Resident Engineer: Paul Brennan
    Construction Contract Value: $20,273,218.75
    Construction Bid Price: $17,682,169.00
    Initial Construction Estimate: $16,893,665.00
    District: District 6

    Contracts (3) Progress
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79510 -- Construction Contract
    Median Barrier Replacement Repairs, Lighting and ITS Improvements along a Section of Interstate 90. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/11/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/02/2011
    Project Initiation Form PIF Entered 08/02/2011
    Project Initiation Form PRC Submitted 08/03/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 10/19/2012
    100% Design 100% Package Comments to DE 11/29/2012
    25% Design 25% Package Received 07/09/2012
    25% Design 25% Package Comments to DE 08/03/2012
    75% Design 75% Package Received 10/19/2012
    75% Design 75% Package Comments to DE 11/29/2012
    Final Design PS&E Received 08/27/2013
    Final Design PS&E to FAPRO 08/28/2013