Project Description:
NEWTON- REPLACEMENT OF ROADWAY LIGHTING STATION #4 ALONG THE I-90 BOSTON EXTENSION
Project involves the replacement of two electrical substations along I-90 Boston Extension
Location:
  • City of Newton
  • Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $79,646.00
    Construction Bid Price: $65,432.00
    Initial Construction Estimate: $75,707.00
    District: District 6

    Contracts (2) Progress
    # 62529 -- Construction Contract
    Replacement of Electrical Substation Number 4 along Interstate 90. Completed
    # 64305 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/07/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/02/2011
    Project Initiation Form PIF Entered 08/02/2011
    Project Initiation Form PRC Submitted 08/03/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 01/26/2013
    Project Management
    100% Design 100% Package Received 10/01/2012
    100% Design 100% Package Comments to DE 11/27/2012
    25% Design 25% Package Received 10/01/2012
    25% Design 25% Package Comments to DE 10/26/2012
    75% Design 75% Package Received 11/27/2012
    75% Design 75% Package Comments to DE 10/01/2012
    Final Design PS&E Received 12/26/2012
    Final Design PS&E to FAPRO 01/23/2013
    Consultant Contract Process Scope to DE 01/31/2012
    Consultant Contract Process NTP Issued 03/12/2012
    Consultant Contract Process Workhours Approved 02/17/2012