Project Description:
BOSTON- BROOKLINE- SUPERSTRUCTURE REPLACEMENT, B-16-055, COMMONWEALTH AVENUE OVER I-90 & MBTA & DECK REPAIR, B-27-018, CARLTON STREET OVER I-90 & MBTA
This project involves the replacement of the bridge superstructure along I-90 at Commonwealth Ave and the repair of the deck at Carlton Street over I-90 and MBTA.
Location:
  • City of Boston
  • Town of Brookline
  • Design Responsibility: Consultant
    Project Manager: Ryan E. McNeill
    Estimated Total Contract Cost: $84,850,126.50
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 05/10/2014 )

    Contracts (8) Progress
    # 55545 -- Design -- Bridge Open End
    Work will consist of reviewing Bridge Project estimates and preparing guidance for estimating of Bridge projects. Final
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64307 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77860 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80661 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/02/2011
    Project Initiation Form PIF Entered 08/02/2011
    Project Initiation Form PRC Submitted 08/03/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 05/10/2014
    Project Management
    Final Design PS&E Received 05/05/2014
    Final Design PS&E Received 06/11/2014
    Final Design PS&E Received 12/12/2014
    Final Design PS&E to FAPRO 06/10/2014