Project Description:
BOSTON- BRIDGE SUPERSTRUCTURE REPLACEMENTS, B-16-043 TREMONT STREET OVER ROUTE I-90 & AMTRAK, B-16-044, ARLINGTON STREET OVER ROUTE I-90 AND AMTRAK, B-16-081, TREMONT AND ARLINGTON STREETS OVER AMTRAK/MBTA
The project involves the superstructure replacement 3 bridges over I-90 at Arlington Street, Tremont Street and Arlington and Tremont street also over Amtrak/MBTA.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Paige Parker
    Estimated Total Contract Cost: $65,126,500.00
    Estimated Total Federal Participating Construction Cost: $68,202,325.00
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/02/2011
    Project Initiation Form PIF Entered 08/02/2011
    Project Initiation Form PRC Submitted 08/08/2011
    Project Review Committee PRC Approved 12/14/2023
    Project Review Committee Letter 08/19/2011
    Project Management