GREENFIELD- BRIDGE REPLACEMENT, G-12-052 (0XR) & G-12-053 (0XT), I-91 (NB & SB) OVER BMRR
The proposed work for Bridge Nos. G-12-052 (0XR) and G-12-053 (0XT) shall consist of removing the existing bridge superstructures and replacing with new superstructures complete with new decks and barriers. The new superstructures shall accommodate two lanes of traffic in their respective directions. The new structures will not feature sidewalks. The bridge rails shall be type CF-PL3 modified with the Type II Protective Screens. Four highway guardrail transitions shall be located at the corners of each bridge. Approximately 100 feet of the existing approach roadways shall be milled and paved on both sides of the bridges.
Location:
  • Town of Greenfield
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Liam Pitrat
    Construction Bid Price: $19,357,752.70
    District: District 2

    Contracts (4) Progress
    # 108809 -- Construction Contract
    2 Bridge Replacements Br. Nos. G-12-052 & G-12-053 (Steel) Interstate 91 (NB & SB) over the Pan Am Railroad Completed
    # 55040 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/06/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2011
    Project Initiation Form PIF Entered 08/04/2011
    Project Initiation Form PRC Submitted 08/04/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 07/13/2019
    Project Management
    100% Design 100% Package Received 01/31/2018
    25% Design 25% Package Received 02/19/2015
    25% Design 25% Package Comments to DE 06/19/2015
    75% Design 75% Package Received 02/28/2017
    75% Design 75% Package Comments to DE 06/27/2017
    75% Design 75% Plans Approved 08/25/2017
    75% Design 75% Plans Complete 08/25/2017
    Final Design PS&E Received 04/29/2019
    Final Design PS&E to FAPRO 06/26/2019