GEORGETOWN- NEWBURY- WEST NEWBURY- NEWBURYPORT- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
The project consists of highway and bridge deck resurfacing, safety and environmental improvements. All 8 lanes will be resurfaced between Milemarkers 77.4 and 86.4 in each direction for a total lane mile resurfacing area of 90.0 miles.
Location:
  • Town of Georgetown
  • Town of Newbury
  • City of Newburyport
  • Town of West Newbury
  • Construction Begins: Spring 2015
    Resident Engineer: David Conroy
    Construction Contract Value: $21,505,527.17
    Construction Bid Price: $16,973,774.70
    Initial Construction Estimate: $18,524,000.00
    District: District 4

    Contracts (1) Progress
    # 86199 -- Construction Contract
    Resurfacing and Related Work (Including 5 Bridges) along Sections of Interstate 95. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/17/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2011
    Project Initiation Form PIF Entered 08/04/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 12/27/2014
    Project Management
    100% Design 100% Package Received 11/03/2014
    100% Design 100% Package Comments to DE 11/17/2014
    25% Design 25% Package Received 07/02/2014
    75% Design 75% Package Received 07/02/2014
    75% Design 75% Package Comments to DE 08/08/2014
    75% Design 75% Package Comments to DE 09/16/2014
    75% Design 75% Package Comments to DE 11/06/2014
    Final Design PS&E Received 11/03/2014
    Final Design PS&E Received 11/21/2014
    Final Design PS&E to FAPRO 12/16/2014