Project Description:
COLRAIN- BRIDGE REPLACEMENT, C-18-028 & NEW CULVERT, C-18-048, ST 112 (JACKSONVILLE ROAD) OVER EAST BRANCH OF NORTH RIVER
The work on this project will consist of the full-replacement of Bridge C-18-028 (0KQ) as well as the full replacement of New Box Culvert C-18-048 (BPJ) in the town of Colrain. The replacement will include the full replacement of the bridge and new box culvert, scour countermeasures, and extended approach work in the southerly approach.
Location:
  • Town of Colrain
  • Resident Engineer: Justin Bourbeau
    Construction Bid Price: $9,575,773.00
    District: District 1

    Contracts (3) Progress
    # 60140 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 90718 -- Construction Contract
    Bridge and Culvert Replacements Nos. C-18-028 & C-18-048 Jacksonville Road (Route 112) over the East Branch of the North River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/28/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/05/2011
    Project Initiation Form PIF Entered 08/05/2011
    Project Initiation Form PRC Submitted 08/05/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 07/14/2015
    25% Design 25% Package Received 02/15/2013
    25% Design 25% Package Received 09/26/2013
    25% Design 25% Package Comments to DE 03/22/2013
    25% Design 25% Package Comments to DE 10/07/2013
    25% Design 25% Package Approved 02/25/2014
    25% Design Design Public Hearing 03/04/2014
    75% Design 75% Package Received 04/13/2015
    75% Design 75% Package Comments to DE 06/04/2015
    75% Design 75% Plans Approved 07/10/2015
    75% Design 75% Plans Complete 07/09/2015
    Final Design PS&E Received 08/31/2015
    Final Design PS&E Received 01/08/2016
    Final Design PS&E Received 02/22/2016
    Final Design PS&E to FAPRO 09/03/2015
    Final Design PS&E to FAPRO 01/11/2016
    Final Design PS&E to FAPRO 02/22/2016
    Consultant Contract Process Scope to DE 08/17/2011
    Consultant Contract Process NTP Issued 09/27/2011
    Consultant Contract Process Workhours Approved 09/16/2011