Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHAMPTON– BRIDGE REPLACEMENT, N-19-059, I-91 OVER US ROUTE 5 AND B&MRR, BRIDGE REPLACEMENT, N-19-060, I-91 OVER HOCKANUM ROAD AND IMPROVEMENTS TO I-91/INTERCHANGE 18
The proposed project will include complete removing and replacing the existing bridge structures. The new superstructures shall accommodate two lanes of traffic in their respective directions. The new structures will not feature sidewalks. The bridge rails shall be type CF-PL3 modified with the Type II Protective Screens. Four highway guardrail transitions shall be located at the corners of each bridge. Approximately 100 feet of the existing approach roadways shall be milled and paved on both ends of the project and between the two bridges.
Location:
  • City of Northampton
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Todd Moylan
    Construction Bid Price: $42,115,135.60
    District: District 2

    Contracts (5) Progress
    # 112337 -- Construction Contract
    Bridge Replacements and Related Work (Including Signals) along a Section of Interstate 91 at Interchange 18, Br. No. N-19-059 (Steel) over Route 5 and B&M Railroad and Br. No. 98% Complete
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80661 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    Contract Dates
    Notice to Proceed: 02/08/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/05/2011
    Project Initiation Form PIF Entered 08/05/2011
    Project Initiation Form PRC Submitted 08/05/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 08/01/2020
    Project Management
    100% Design 100% Package Received 03/25/2020
    25% Design 25% Package Received 01/31/2014
    25% Design 25% Package Received 04/08/2016
    25% Design 25% Package Received - Resub 1 04/06/2016
    25% Design Design Public Hearing 04/24/2019
    75% Design 75% Package Received 08/26/2019
    75% Design 75% Package Comments to DE 11/05/2019
    75% Design 75% Package Received - Resub 1 12/16/2019
    Final Design PS&E Received 08/25/2020
    Final Design PS&E to FAPRO 06/29/2020
    Consultant Contract Process Scope to DE 09/26/2011
    Consultant Contract Process NTP Issued 05/13/2015
    Consultant Contract Process Workhours Approved 01/09/2012