NORTHAMPTON- ROUNDABOUT CONSTRUCTION AT INTERSECTION ROUTES 5/10 (NORTH KING STREET) & HATFIELD STREET
The proposed project will improve safety and operations at the intersection of Routes 5&10 and Hatfield St. Poor geometry and excessive delays to the side street traffic will be eliminated by construction of a modern roundabout at this northern gateway to the City of Northampton.
Location:
  • City of Northampton
  • Construction Begins: Spring 2020
    Resident Engineer: Joseph Burek
    Construction Bid Price: $3,399,264.00
    District: District 2

    Contracts (2) Progress
    # 109688 -- Construction Contract
    Roundabout Construction and Related Work (Including Lighting) at (Routes 5/10) North King and Hatfield Streets Completed
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/21/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/08/2011
    Project Initiation Form PIF Received 08/08/2011
    Project Initiation Form PIF Entered 08/08/2011
    Project Initiation Form PRC Submitted 08/08/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/18/2011
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 08/02/2019
    100% Design 100% Package Comments to DE 08/27/2019
    25% Design 25% Package Received 04/10/2013
    25% Design 25% Package Comments to DE 09/16/2013
    25% Design Design Public Hearing 03/06/2017
    75% Design 75% Package Received 04/10/2018
    75% Design 75% Package Comments to DE 06/18/2018
    Final Design PS&E Received 10/09/2019
    Final Design PS&E to FAPRO 08/28/2019