Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
PAXTON- RESURFACING AND RELATED WORK ON ROUTE 122, FROM ROUTE 31 TO THE RUTLAND T.L.
The work includes cold planing and resurfacing; replacing berm; and replacing existing and installing new guardrail and end treatment upgrades as needed. Incidental work includes installing permanent pavement markings, sign replacement, and instituting traffic controls during construction operations.
Location:
  • Town of Paxton
  • Resident Engineer: Dariusz Wisniewski
    Construction Contract Value: $1,389,407.17
    Construction Bid Price: $1,201,821.07
    Initial Construction Estimate: $1,308,000.00
    District: District 3

    Contracts (1) Progress
    # 84987 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 122 (Pleasant Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/28/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/08/2011
    Project Initiation Form PIF Entered 08/08/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 09/08/2014
    25% Design 25% Package Received 12/06/2013
    25% Design 25% Package Comments to DE 03/13/2014
    75% Design 75% Package Received 12/06/2013
    75% Design 75% Package Comments to DE 03/13/2014
    Final Design PS&E Received 09/08/2014
    Final Design PS&E to FAPRO 09/09/2014