Project Description:
OAKHAM- RUTLAND- RESURFACING & RELATED WORK ON ROUTE 122, FROM ROUTE 122A IN RUTLAND TO THE OAKHAM/BARRE T.L.
This project consists of resurfacing Route 122 in Oakham and Rutland. The southern limit of this project is the southern end of the median at the intersection with Route 122A in Rutland (mm 39.0±). The northern limit of this project is the Oakham / Barre Town Line (mm 43.7±). The total length of this project is approximately 4.7 miles. The scope of work includes: micromilling and resurfacing of the mainline; installing recessed polyurea pavement markings throughout this project; clearing and grubbing to re-establish clear zones; adjusting, rebuilding, and remodeling drainage structures; replacing all frames and grates with hook-lock frames and grates; resetting existing salvageable guardrail; and replacing existing substandard guardrail.
Location:
  • Town of Oakham
  • Town of Rutland
  • Resident Engineer: Dariusz Wisniewski
    Construction Contract Value: $3,239,235.00
    Construction Bid Price: $2,578,057.57
    Initial Construction Estimate: $2,554,166.67
    District: District 3

    Contracts (1) Progress
    # 78962 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 122 (Barre Paxton and Worcester Roads). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/08/2011
    Project Initiation Form PIF Entered 08/08/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Status Advertised 08/03/2013
    Project Management
    25% Design 25% Package Received 06/18/2013
    75% Design 75% Package Received 06/18/2013
    75% Design 75% Package Comments to DE 07/03/2013
    Final Design PS&E Received 07/30/2013
    Final Design PS&E to FAPRO 07/31/2013