CHELSEA- FIBER OPTIC COMMUNICATION CONNECTION BETWEEN THE EOPSS DATA CENTER & THE TOBIN BRIDGE
MassDOT was awarded a grant from EOPSS for $7,032,000 for the Massachusetts Emergency Transportation Fiber Network (METFON). This project is one of five construction projects tht will link various transportation operations centers together with fiber optics.
Location:
  • City of Chelsea
  • Resident Engineer: Kathryn Barr
    Construction Contract Value: $2,700,240.00
    Construction Bid Price: $2,312,382.75
    Initial Construction Estimate: $1,047,210.00
    District: District 6

    Contracts (2) Progress
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 72209 -- Construction Contract
    Fiber Optic Cable Installation Connecting the EOPSS Data Center and the Maurice J. Tobin Memorial Bridge. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/15/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/08/2011
    Project Initiation Form PIF Entered 08/08/2011
    Project Initiation Form PRC Submitted 08/08/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 12/17/2011
    Project Management
    100% Design 100% Package Received 12/14/2011
    25% Design 25% Package Received 11/29/2011
    75% Design 75% Package Received 11/29/2011
    Final Design PS&E Received 12/14/2011
    Final Design PS&E to FAPRO 12/15/2011