Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- SCHEDULED & EMERGENCY DRAWBRIDGE OPERATIONS, REPAIRS, AND MAINTENANCE IN THE NORTH AREA
These are drawbridge operation, repair and maintenance contracts that according to Coast Guard Regulations are always required. The current contract # 64165 (Projis # 605890) has a contract completion date of July 11, 2012. The new contract must be in place before the expiry of the current contract.
Location:
Resident Engineer: Julia Whiteneck
Construction Contract Value: $1,815,335.00
Construction Bid Price: $995,885.00
Initial Construction Estimate: $1,482,375.00
District: District 4

Contracts (1) Progress
# 76289 -- Construction Contract
Drawbridge Operation (North Area) Scheduled and Emergency Repairs and Maintenance District-wide. 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/04/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/09/2011
    Project Initiation Form PIF Entered 08/09/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 04/28/2012
    Project Status Advertised 10/20/2012
    Project Management
    Final Design PS&E Received 09/13/2012
    Final Design PS&E to FAPRO 03/20/2012