Project Description:
STERLING- INTERSTATE MAINTENANCE & RELATED WORK ON I-190
The project consists of highway and bridge deck resurfacing, safety and environmental improvements. All 6 lanes will be resurfaced between Milemarkers 8.7 and 15.7 in each direction for a total lane mile resurfacing area of 7.0 miles.
Location:
  • Town of Sterling
  • Construction Begins: Summer 2018
    Resident Engineer: Patrick Marion
    Construction Bid Price: $19,170,578.57
    District: District 3

    Contracts (1) Progress
    # 102202 -- Construction Contract
    Resurfacing and Related Work (Including Repairs to 6 Bridges) on a Section of Interstate 190. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/30/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/09/2011
    Project Initiation Form PIF Entered 08/09/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 07/31/2017
    25% Design 25% Package Received 06/20/2017
    25% Design 25% Package Comments to DE 07/05/2017
    75% Design 75% Package Received 06/20/2017
    75% Design 75% Package Comments to DE 07/05/2017
    Final Design PS&E Received 07/31/2017
    Final Design PS&E to FAPRO 08/28/2017