Project Description:
EASTHAMPTON- NORTHAMPTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-91 FROM MM 21.2 TO MM 26.9 IN BOTH DIRECTIONS (6.1 MILES)
The project consists of highway and bridge deck resurfacing resurfacing, safety and environmental improvements between Mile Markers 21.2 and 26.9 in both directions for a total project length of 6.1 miles.
Location:
  • Town of Easthampton
  • City of Northampton
  • Construction Begins: Autumn 2014
    Resident Engineer: William Whiteman
    Construction Contract Value: $19,478,904.17
    Construction Bid Price: $13,317,989.95
    Initial Construction Estimate: $11,548,152.50
    District: District 2

    Contracts (1) Progress
    # 81502 -- Construction Contract
    Resurfacing and Related Work (Including 11 Bridges) along Sections of Interstate 91. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/07/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/09/2011
    Project Initiation Form PIF Entered 08/09/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/22/2011
    Project Status Advertised 03/22/2014
    Project Management
    100% Design 100% Package Received 07/25/2013
    100% Design 100% Package Received 11/19/2013
    100% Design 100% Package Comments to DE 10/02/2013
    25% Design 25% Package Received 04/09/2013
    25% Design 25% Package Comments to DE 05/21/2013
    75% Design 75% Package Received 04/09/2013
    75% Design 75% Package Comments to DE 05/21/2013
    Final Design PS&E Received 01/29/2014
    Final Design PS&E to FAPRO 01/29/2014