| Project Description: |
DISTRICT 3- CONCRETE COATING (ASR MITIGATION) APPLICATION ON MEDIAN BARRIERS AT VARIOUS LOCATIONS ON I-90
The work in this project consists of pressure washing concrete surfaces that show ASR cracking and applying a concrete surface coating.
|
| Location: | |
| Resident Engineer: | Kit Leong![]() |
| Construction Contract Value: | $344,140.00 |
| Construction Bid Price: | $201,265.00 |
| Initial Construction Estimate: | $302,500.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||