Project Description:
CHATHAM- IMPROVEMENTS ON MAIN STREET (ROUTE 28), FROM GEORGE RYDER ROAD TO BARN HILL ROAD
The purpose of this project is to construct safety and multimodal improvements along a 2700 foot linear segment of Main Street (Route 28) between George Ryder Road and Barn Hill Road. The intent of the project is to provide improved safety and accessibility for bicyclists, pedestrians and motorists traveling through this corridor.
Location:
  • Town of Chatham
  • Construction Begins: Autumn 2018
    Resident Engineer: Michael King
    Construction Bid Price: $3,495,908.60
    District: District 5

    Contracts (3) Progress
    # 104049 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of (Route 28) Main Street Completed
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86792 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/29/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2011
    Project Initiation Form PIF Entered 09/07/2011
    Project Initiation Form PRC Submitted 09/07/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 05/26/2018
    Project Management
    100% Design 100% Package Received 07/07/2016
    100% Design 100% Package Comments to DE 12/06/2016
    100% Design 100% Package Received - Resub 1 02/27/2017
    100% Design 100% Plans Approved 07/03/2017
    25% Design 25% Package Received 03/04/2014
    25% Design 25% Package Comments to DE 12/08/2014
    25% Design Design Public Hearing 02/19/2015
    75% Design 75% Package Received 06/30/2015
    75% Design 75% Package Comments to DE 10/06/2015
    Final Design PS&E Received 11/07/2017
    Final Design PS&E to Peer Reviewer 08/04/2016
    Final Design Peer Review Comments to DE 08/24/2016
    Final Design PS&E Received - Resub 2 01/31/2018
    Final Design PS&E Received - Resub 3 04/04/2018