PALMER- BRIDGE PRESERVATION. P-01-046, I-90 OVER QUABOAG RIVER, P-01-047, I-90 OVER NECRR & MCRR & P-01-049, I-90 OVER ROUTE 181 (SYKES STREET)
Project consists of bridge deck repairs, new waterproofing membrane, deck joint replacement and resurfacing.
Location:
  • Town of Palmer
  • Construction Begins: Summer 2016
    Resident Engineer: Michael DeSimone
    Construction Bid Price: $4,047,710.00
    District: District 2

    Contracts (1) Progress
    # 93965 -- Construction Contract
    Bridge Rehabilitation and Related Work (Including Painting) to 3 Bridges along Interstate 90 (Br. Nos. P-01-046, P-01-047 & P-01-049). (Re-Advertised Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/27/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2011
    Project Initiation Form PIF Entered 09/13/2011
    Project Initiation Form PRC Submitted 09/13/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 03/07/2015
    Project Status Advertised 04/23/2016
    Project Management
    100% Design 100% Package Received 12/13/2012
    25% Design 25% Package Received 08/20/2012
    Final Design PS&E Received 05/22/2014
    Final Design PS&E Received 03/01/2016
    Final Design PS&E to FAPRO 05/28/2014