Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHICOPEE- TRAFFIC SIGNAL IMPROVEMENTS & RAMP RESURFACING @ I-90 (INTERCHANGE 6) INCLUDING REPAIRS TO C-13-026
The purpose of this project is to increase vehicle capacity through Interchange 6 between I-90 and I-291 and to improve traffic signalization. The project consists of roadway reconstruction, widening, and micromilling and resurfacing at Interchange 6 and on sections of I-291 and Burnett Road in Chicopee. The roadway work begins north of the American Legion Memorial Bridge ends on I-90 Entrance Ramp A. Proposed reconstructed areas on this project include a large radius triple left turn ramp onto I-291 from I-90, new tandem truck parking lot entrance and exit ramps off the mainline, and a realigned ramp onto I-291 eastbound from Fuller Road. Widened areas on this project include a section of I-291 westbound and the ramps from I-291 to I-90. I-291 will be widened for better alignment with Burnett Road and with the proposed triple left turn lanes from I-90 and the ramps will be widened for a second travel lane. Other work included under this contract includes traffic signal improvements on I-291 and Burnett Road, a new 8 foot wide sidewalk connecting Burnett Road with the American Legion Memorial Bridge, new wheelchair ramps, new drainage structures, pipes, and paved waterways, new traffic signs, new pavement markings, minor tree clearing to improve sight distances, and erosion and sedimentation control.
Location:
  • City of Chicopee
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Victoria Hayes
    Construction Bid Price: $8,372,858.50
    District: District 2

    Contracts (2) Progress
    # 113124 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Bridge Repairs, Highway Lighting and Signals) along a Section of Burnett Road and Interstates 90 & 291 Ramps at Interchange Completed
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/12/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2011
    Project Initiation Form PIF Entered 09/06/2011
    Project Initiation Form PRC Submitted 09/13/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 10/03/2020
    Project Management
    100% Design 100% Package Received 07/12/2016
    100% Design 100% Package Comments to DE 07/17/2019
    100% Design 100% Package Received - Resub 1 06/14/2019
    100% Design 100% Package Received - Resub 2 12/27/2019
    25% Design 25% Package Received 11/19/2012
    75% Design 75% Package Received 05/13/2015
    75% Design 75% Package Comments to DE 10/13/2015
    Final Design PS&E Received 05/18/2020
    Final Design PS&E to FAPRO 09/28/2020