Project Description:
DISTRICT 4- SCHEDULED & EMERGENCY DECK & JOINT REPAIRS AT VARIOUS LOCATIONS
The work to be done under this project consist of scheduled and emergency deck/joint repairs including repairs to the sidewalk and approach slab. The work includes concrete as well as wooden deck repairs including milling and resurfacing and also asphalt-rubber surface treatment with aggregate cover on wooden decks.
Location:
Resident Engineer: Michael Gilardi
Construction Contract Value: $4,935,510.00
Construction Bid Price: $2,082,510.00
Initial Construction Estimate: $2,587,800.00
District: District 4

Contracts (1) Progress
# 72756 -- Construction Contract
Scheduled and Emergency Bridge Deck and Joint Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/02/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/19/2011
    Project Initiation Form PIF Entered 09/19/2011
    Project Initiation Form PRC Submitted 09/19/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 02/18/2012
    Project Management
    Final Design PS&E Received 12/15/2011
    Final Design PS&E to FAPRO 02/13/2012