Project Description:
DANVERS- BRIDGE REPLACEMENT, D-03-013, ROUTE 35 (WATER STREET) OVER WATERS RIVER
(Replaces original #601918). A longer 2-span bridge totaling 138 feet will replace the existing Waters Street over Waters River culvert at its present location. The new bridge opening will be 3 times larger than the existing opening to improve tidal flushing and prevent upstream tidal backups. The width of roadway will be maintained and the sidewalk replaced.
Location:
  • Town of Danvers
  • Resident Engineer: Carmen Ilardi
    Construction Contract Value: $8,208,177.00
    Construction Bid Price: $6,160,434.46
    Initial Construction Estimate: $7,740,377.00
    District: District 4

    Contracts (6) Progress
    # 54827 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75355 -- Construction Contract
    Bridge Replacement (D-03-013) (Concrete) - Water Street (Route 35) over Waters River. Completed
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/28/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/22/2011
    Project Initiation Form PIF Entered 09/22/2011
    Project Initiation Form PRC Submitted 09/22/2011
    Project Review Committee PRC Approved 12/11/1996
    Project Status Advertised 09/01/2012
    Project Management
    100% Design 100% Package Received 08/13/2007
    100% Design 100% Package Received 04/27/2012
    100% Design 100% Package Comments to DE 06/22/2012
    25% Design 25% Package Received 01/06/2000
    25% Design Design Public Hearing 03/18/1999
    75% Design 75% Package Received 08/06/2002
    Final Design PS&E Received 07/18/2012
    Final Design PS&E to FAPRO 08/22/2012
    Consultant Contract Process Scope to DE 07/20/2011
    Consultant Contract Process NTP Issued 10/06/2011
    Consultant Contract Process Workhours Approved 09/29/2011