Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AMHERST- BELCHERTOWN- EASTHAMPTON- ERVING- HADLEY- MONTAGUE- NORTHAMPTON- NORTHFIELD- WILLIAMSBURG- BAYSTATE GREENWAY SIGNING
MassDOT designated a 740-mile network of bicycle routes across the Commonwealth as part of the 2008 Massachusetts Bicycle Transportation Plan. This network, known as the Bay State Greenway (BSG), covers shared use paths and on-road facilities in seven corridors. This project constitutes the Bay State Greenway Connecticut River Corridor/Pioneer Valley Pilot. Under this project, MassDOT will implement the BSG in Districts 1 and 2 by installing signs on existing posts along the Franklin County Bikeway, on two state highway segments, and on shared use paths throughout the region.
Location:
  • Town of Amherst
  • Town of Belchertown
  • Town of Easthampton
  • Town of Erving
  • Town of Hadley
  • Town of Montague
  • City of Northampton
  • Town of Northfield
  • Town of Williamsburg
  • Resident Engineer: Victoria Hayes
    Construction Contract Value: $46,461.00
    Construction Bid Price: $40,782.80
    Initial Construction Estimate: $51,344.00
    District: District 2

    Contracts (1) Progress
    # 72752 -- Construction Contract
    Installation of Bikeway Signing for the Baystate Greenway. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/26/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/13/2011
    Project Initiation Form PIF Entered 10/13/2011
    Project Initiation Form PRC Submitted 10/21/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 02/18/2012
    Project Management
    100% Design 100% Package Received 12/09/2011
    Final Design PS&E Received 02/06/2012
    Final Design PS&E to FAPRO 02/14/2012