Project Description:
HOPKINTON- WESTBOROUGH- BRIDGE REPLACEMENT, H-23-006=W-24-016, FRUIT STREET OVER CSX & SUDBURY RIVER
Bridge H-23-006=W-24-016 is both posted and structurally deficient. It is currently posted for 9-16-26 tons. It is currently rated 6-4-4. This structure has 4 spans and 3 piers. It spans both the CSX Railroad & Sudbury River. It has been recommended for replacement by the District 3 DBIE & DBE.
Location:
  • Town of Hopkinton
  • Town of Westborough
  • Construction Begins: Autumn 2020
    Resident Engineer: Scott Kallin
    Construction Bid Price: $11,078,907.99
    District: District 3

    Contracts (4) Progress
    # 111303 -- Construction Contract
    Bridge Replacement Br. No. H-23-006=W-24-016 (Steel) Fruit Street over CSX Railroad and the Sudbury River Completed
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 68387 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/20/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/20/2011
    Project Initiation Form PIF Entered 10/20/2011
    Project Initiation Form PRC Submitted 10/20/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 07/05/2019
    100% Design 100% Package Comments to DE 10/25/2019
    25% Design 25% Package Received 11/17/2016
    25% Design 25% Package Comments to DE 02/06/2017
    25% Design 25% Package Approved 04/14/2017
    25% Design Design Public Hearing 05/11/2017
    25% Design 25% Plans Complete 02/16/2017
    75% Design 75% Package Received 10/11/2017
    75% Design 75% Package Received 11/07/2018
    75% Design 75% Package Comments to DE 03/01/2018
    75% Design 75% Package Received - Resub 2 01/18/2018
    75% Design 75% Package Received - Resub 3 11/07/2018
    75% Design 75% Plans Approved 03/20/2018
    75% Design 75% Plans Complete 03/20/2018
    Final Design PS&E Received 12/04/2019
    Final Design PS&E to FAPRO 02/12/2020
    Final Design PS&E Received - Resub 1 04/24/2020