Project Description:
WEYMOUTH- BRAINTREE- RESURFACING & RELATED WORK ON ROUTE 3
The resurfacing project begins at STA 238+50 (MM-38.2) in Weymouth and follows the mainline of Route 3 northerly through Weymouth into Braintree ending at STA 457+00 (MM-42.3). The south bound end of project starts at STA 457+00 (MM-42.3) and continues southerly through Braintree into Weymouth and ends at STA 238+50 (MM 38.2). The 6 lanes on the mainline and the median and breakdown shoulders shall be included. The exit and entrance ramps at Union Street shall also be included; however the circle under Route 3 at Union Street will not be included. The entrance and exit ramps at Route 18 / Main Street clover leaf shall be included. The total project length will be approximately 4.14 miles-(8.28 miles North and South Route 3). The ADT is approximately 125,000 vpd.
Location:
  • Town of Braintree
  • Town of Weymouth
  • Resident Engineer: Kevin Fuller
    Construction Contract Value: $12,139,033.53
    Construction Bid Price: $10,587,778.63
    Initial Construction Estimate: $9,430,745.00
    District: District 6

    Contracts (3) Progress
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 81505 -- Construction Contract
    Resurfacing and Related Work (Including 5 Bridges) along a Section of Route 3. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/25/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/26/2011
    Project Initiation Form PIF Entered 11/04/2011
    Project Initiation Form PRC Submitted 11/04/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 03/22/2014
    Project Management
    100% Design 100% Package Received 10/25/2013
    100% Design 100% Package Comments to DE 11/04/2013
    75% Design 75% Package Received 05/28/2013
    75% Design 75% Package Comments to DE 07/31/2013
    Final Design PS&E Received 12/23/2013
    Final Design PS&E to FAPRO 12/24/2013