Project Description:
BOSTON- IMPROVEMENTS TO PUMP STATIONS 1, 2, AND 4 ALONG I-90 (BOSTON EXTENSION)
The project involves rehabilitation and replacement of the existing pumps and electrical controls at three Pump Stations (PS1, PS2, and PS4) along the I-93 CA/T project. The project also involves the connection of the new systems and controls to the main MassDOT Operations Center.
Location:
  • City of Boston
  • Construction Begins: Spring 2018
    Resident Engineer: Michael Lemire
    Construction Bid Price: $4,029,830.00
    District: District 6

    Contracts (3) Progress
    # 100742 -- Construction Contract
    Repairs and Improvements to Pump Stations 1, 2 and 4 along Interstate 90. Completed
    # 60283 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/25/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2011
    Project Initiation Form PIF Entered 11/14/2011
    Project Initiation Form PRC Submitted 11/14/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 06/17/2017
    Project Management
    100% Design 100% Package Received 10/07/2013
    100% Design 100% Package Comments to DE 11/13/2013
    25% Design 25% Package Received 08/07/2012
    25% Design 25% Package Comments to DE 11/30/2012
    75% Design 75% Package Received 01/24/2013
    75% Design 75% Package Comments to DE 02/15/2013
    Final Design PS&E Received 12/09/2015
    Final Design PS&E to FAPRO 06/12/2017
    Consultant Contract Process Scope to DE 02/03/2012
    Consultant Contract Process NTP Issued 05/17/2012
    Consultant Contract Process Workhours Approved 04/26/2012