Project Description:
BOSTON- HVAC CONTROLS UPGRADE WITHIN 8 BUILDINGS, ALONG I-90 CONNECTOR TUNNEL & TED WILLIAMS TUNNEL
The contract will involve the replacement of obsolete equipment within 8 different buildings adjacent to (and servicing) the CA/T project.
Location:
  • City of Boston
  • Construction Begins: Summer 2014
    Resident Engineer: Anthony DiDio
    Construction Contract Value: $2,071,176.00
    Construction Bid Price: $1,798,240.00
    Initial Construction Estimate: $2,546,300.00
    District: District 6

    Contracts (2) Progress
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 81025 -- Construction Contract
    HVAC Control Upgrades to 8 Buildings along the Ted Williams Tunnel (Interstate 90). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/20/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2011
    Project Initiation Form PIF Entered 11/14/2011
    Project Initiation Form PRC Submitted 11/14/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 01/25/2014
    Project Management
    100% Design 100% Package Received 10/22/2013
    100% Design 100% Package Comments to DE 11/13/2013
    25% Design 25% Package Received 11/20/2012
    25% Design 25% Package Comments to DE 12/31/2012
    75% Design 75% Package Received 11/20/2012
    75% Design 75% Package Comments to DE 12/31/2012
    Final Design PS&E Received 01/10/2014
    Final Design PS&E to FAPRO 01/22/2014
    Consultant Contract Process Scope to DE 02/09/2012
    Consultant Contract Process NTP Issued 04/24/2012
    Consultant Contract Process Workhours Approved 04/16/2012