Project Description:
BOSTON- SUMNER & CALLAHAN TUNNEL VENT BUILDING AND CALLAHAN PUMP STATION MECHANICAL AND ELECTRICAL UPGRADES
The project consists of replacing the 13.8v switchgears in Vent Buildings; 10, 11, 12 & 13, installing new generators, lighting, SCADA and electrical systems for the four vent buildings and replacing pumps at both the Callahan and Sumner mid-river pump stations.
Location:
  • City of Boston
  • Construction Begins: Summer 2021
    Resident Engineer: Daniel Burke
    Construction Bid Price: $37,249,000.00
    District: District 6

    Contracts (3) Progress
    # 113976 -- Construction Contract
    Sumner and Callahan Tunnel Vent Buildings and Pump Stations Mechanical and Electrical Improvements (Re-Advertised Project) 97% Complete
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/12/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2011
    Project Initiation Form PIF Entered 11/14/2011
    Project Initiation Form PRC Submitted 11/14/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 11/09/2019
    Project Status Advertised 02/06/2021
    Project Management
    100% Design 100% Package Received 05/22/2015
    100% Design 100% Package Comments to DE 06/30/2015
    25% Design 25% Package Received 11/28/2012
    25% Design 25% Package Comments to DE 01/23/2013
    75% Design 75% Package Received 03/14/2014
    75% Design 75% Package Comments to DE 06/30/2014
    Final Design PS&E Received 05/20/2016
    Final Design PS&E to Peer Reviewer 09/07/2016
    Final Design Peer Review Comments to DE 09/27/2016
    Final Design PS&E Received - Resub 1 12/15/2017
    Final Design PS&E Received - Resub 2 12/17/2020