Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHARLTON- SOUTHBRIDGE- RESURFACING & RELATED WORK ON ROUTE 169, FROM ROUTE 20 TO 400 FEET SOUTH OF VINTON STREET
This project consists of resurfacing Route 169 in Charlton and Southbridge. The southern limit is 400 feet south of Vinton Street in Southbridge (mm 5.0 ±). The northern limit is Route 20 in Charlton (mm 9.1 ±). The total length of this project is approximately 4.1 miles. The scope of work includes: micromilling and resurfacing the mainline; installing recessed polyurea pavement markings throughout the project; clearing and grubbing to re-establish clear zones; replacing sidewalks and wheelchair ramps as necessary; adjusting, rebuilding, and remodeling drainage structures; and replacing all frames and grates with cascade style hook-lock frames and grates.
Location:
  • Town of Charlton
  • Town of Southbridge
  • Resident Engineer: Hassan Valipour
    Construction Contract Value: $4,492,012.43
    Construction Bid Price: $3,940,790.85
    Initial Construction Estimate: $3,800,000.00
    District: District 3

    Contracts (1) Progress
    # 85014 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 169 (Southbridge Road and Worcester Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/28/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/15/2011
    Project Initiation Form PIF Entered 11/15/2011
    Project Initiation Form PRC Submitted 11/15/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 09/03/2014
    25% Design 25% Package Received 02/03/2014
    25% Design 25% Package Comments to DE 02/25/2014
    75% Design 75% Package Received 02/03/2014
    75% Design 75% Package Comments to DE 02/25/2014
    Final Design PS&E Received 09/03/2014
    Final Design PS&E to FAPRO 09/16/2014