Project Description:
MONSON- PALMER- RESURFACING & RELATED WORK ON ROUTE 32, FROM MM 5.69 TO MM 6.88 AND FROM MM 8.24 TO MM 8.80 AT ROUTE 20 (1.69 MILES)
Project consists of resurfacing Route 32 in the towns of Monson and Palmer. Limits will be from beginning of State Highway in Monson at MM 5.69 to MM 6.88 and from MM8.24 to Route 20 in Palmer at MM 8.80. South Main Street from Route 32 to Conant Street will also be resurfaced. New pavement markings, sidewalk replacement, and signage will be included.
Location:
  • Town of Monson
  • Town of Palmer
  • Resident Engineer: Victoria Hayes
    Construction Contract Value: $1,641,004.10
    Construction Bid Price: $1,478,081.00
    Initial Construction Estimate: $1,310,000.00
    District: District 2

    Contracts (1) Progress
    # 84986 -- Construction Contract
    Resurfacing and Related Work along Sections of Route 32 (Palmer Road and South Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/05/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/16/2011
    Project Initiation Form PIF Entered 11/16/2011
    Project Initiation Form PRC Submitted 11/16/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 05/07/2014
    100% Design 100% Package Comments to DE 06/30/2014
    25% Design 25% Package Received 09/12/2013
    75% Design 75% Package Received 09/12/2013
    75% Design 75% Package Comments to DE 10/07/2013
    Final Design PS&E Received 07/11/2014
    Final Design PS&E Received 08/05/2014
    Final Design PS&E to FAPRO 08/28/2014