AMESBURY- POWWOW RIVERWALK CONSTRUCTION AT WATER STREET
(Replaces #602343) The project involves the construction of a bicycle and pedestrian pathway along Water Street, continuing 660 feet along the Back River and Powwow River.
Location:
  • Town of Amesbury
  • Construction Begins: Summer 2018
    Resident Engineer: Raymond Orsini
    Construction Bid Price: $575,422.00
    District: District 4

    Contracts (2) Progress
    # 102191 -- Construction Contract
    Construction of the Powwow Riverwalk Multi-Use Path at Heritage Park along Water Street. Completed
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/28/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2011
    Project Initiation Form PIF Entered 11/21/2011
    Project Initiation Form PRC Submitted 11/21/2011
    Project Review Committee PRC Approved 11/21/2011
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 04/18/2017
    100% Design 100% Package Comments to DE 06/02/2017
    25% Design 25% Package Received 01/17/2013
    25% Design 25% Package Comments to DE 04/09/2013
    25% Design 25% Package Received - Resub 1 01/22/2014
    25% Design 25% Package Received - Resub 2 09/19/2016
    25% Design Design Public Hearing 02/16/2017
    75% Design 75% Package Received 04/18/2017
    75% Design 75% Package Comments to DE 06/02/2017
    Final Design PS&E Received 08/01/2017
    Final Design PS&E to Peer Reviewer 05/04/2017
    Final Design Peer Review Comments to DE 06/01/2017
    Final Design PS&E to FAPRO 08/31/2017