Project Description: |
WORCESTER- CLEANING & PAINTING OF 4 BRIDGES, W-44-100, W-44-101, W-44-114, ALONG I-290
This is a structures maintenance contract. Bridge No. W-44-100(1KH) – I-290 Ramp A, Over I-290, Millbrook St., & Ramp C. Bridge No. W-44-101(1TG) – I-290 Ramp C, Over I-290& Millbrook St. Bridge No. W-44-114(1TM) – I-290 EB Over Plantation St. Bridge No. W-44-114(1TN) – I-290 WB Over Plantation St.
|
Location: |
|
Resident Engineer: | Peter Kurt |
Construction Contract Value: | $2,241,210.00 |
Construction Bid Price: | $1,921,100.00 |
Initial Construction Estimate: | $2,062,450.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|