| Project Description: |
WORCESTER- CLEANING & PAINTING OF 4 BRIDGES, W-44-100, W-44-101, W-44-114, ALONG I-290
This is a structures maintenance contract. Bridge No. W-44-100(1KH) – I-290 Ramp A, Over I-290, Millbrook St., & Ramp C. Bridge No. W-44-101(1TG) – I-290 Ramp C, Over I-290& Millbrook St. Bridge No. W-44-114(1TM) – I-290 EB Over Plantation St. Bridge No. W-44-114(1TN) – I-290 WB Over Plantation St.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Harry Adolphe![]() |
| Estimated Total Contract Cost: | $2,241,210.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||