Project Description:
DISTRICT 5- GUARDRAIL & BARRIER SYSTEMS REPAIR & UPGRADE AT VARIOUS LOCATIONS (AREAS ABCD)
Contract will address damaged guardrail sections not repairable through the accident recovery programs. Contract will also provide a means to install new section of guardrail and barrier.
Location:
Resident Engineer: Kyle Fahey
Construction Contract Value: $1,084,577.50
Construction Bid Price: $754,577.50
Initial Construction Estimate: $847,115.00
District: District 5

Contracts (1) Progress
# 72264 -- Construction Contract
Guardrail and Cable Barrier System Repairs and Improvements at Various Locations in Area A. B, C and D. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/14/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/25/2011
    Project Initiation Form PIF Entered 11/25/2011
    Project Initiation Form PRC Submitted 12/05/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 12/24/2011
    Project Management
    Final Design PS&E Received 12/20/2011
    Final Design PS&E to FAPRO 12/21/2011