Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STURBRIDGE- CULVERT REPLACEMENT @ ROUTE 20 & SNELL STREET
The existing structurally deficient culvert was further damaged by Hurrican Irene and requires complete replacement.
Location:
  • Town of Sturbridge
  • Construction Begins: Summer 2020
    Resident Engineer: Ryan Davison
    Construction Bid Price: $3,448,561.25
    District: District 3

    Contracts (3) Progress
    # 111306 -- Construction Contract
    Replacement of Culvert No. S-30-022 (Precast Concrete) and Related Work on a Section of Main Street (Route 20) over Cedar Meadow Brook Completed
    # 115744 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/31/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/12/2011
    Project Initiation Form PIF Entered 01/27/2012
    Project Initiation Form PRC Submitted 01/27/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 06/15/2018
    100% Design 100% Package Comments to DE 08/01/2018
    100% Design 100% Plans Approved 08/01/2018
    100% Design 100% Plans Complete 08/01/2018
    25% Design 25% Package Received 03/07/2016
    25% Design 25% Package Comments to DE 06/23/2016
    75% Design 75% Package Received 05/18/2017
    75% Design 75% Package Received 07/27/2017
    75% Design 75% Package Comments to DE 06/23/2017
    75% Design 75% Package Rejected 06/23/2017
    75% Design 75% Package Received - Resub 1 07/26/2017
    75% Design 75% Plans Approved 09/20/2017
    75% Design 75% Plans Complete 09/14/2017
    Final Design PS&E Received 01/17/2019
    Final Design PS&E to FAPRO 04/27/2020
    Final Design PS&E Received - Resub 1 11/27/2019