Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIMFIELD- PALMER- WARREN- RESURFACING & RELATED WORK & STORMWATER IMPROVEMENTS ON SECTIONS OF I-90 (BETWEEN MM 61.4 & MM 69.6) (8.2 MILES)
The work shall consist of milling and resurfacing travel lanes at deteriorated sections of Route I-90 between MM 61.4 and MM 69.6. The work includes installing painted pavement markings, installing reflectorized slotted pavement markers, traffic controls and erosion/sedimentation control measures. The milling and paving operations shall be coordinated to pave and mill in each work shift
Location:
  • Town of Brimfield
  • Town of Palmer
  • Town of Warren
  • Resident Engineer: Michael DeSimone
    Construction Contract Value: $3,930,693.70
    Construction Bid Price: $2,294,011.20
    Initial Construction Estimate: $2,150,516.00
    District: District 2

    Contracts (1) Progress
    # 77674 -- Construction Contract
    Roadway Resurfacing and Related Work along a Section of Interstate 90. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/18/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/19/2011
    Project Initiation Form PIF Entered 12/19/2011
    Project Initiation Form PRC Submitted 12/19/2011
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 05/25/2013
    Project Management
    25% Design 25% Package Received 08/21/2012
    75% Design 75% Package Received 08/21/2012
    Final Design PS&E Received 11/15/2012
    Final Design PS&E Received 12/06/2012
    Final Design PS&E Received 12/12/2012
    Final Design PS&E to FAPRO 05/22/2013