CONWAY- RETAINING WALL REPLACEMENT ON ROUTE 116 ALONG THE SOUTH RIVER
(Replaces #80822) The existing retaining wall along Route 116 and the South River in Conway will be replaced. The new wall will be constructed within the same footprint of the existing wall.
Location:
  • Town of Conway
  • Resident Engineer: Michael Dostal
    Construction Contract Value: $3,417,763.20
    Construction Bid Price: $3,169,694.00
    Initial Construction Estimate: $4,471,789.50
    District: District 1

    Contracts (3) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 79594 -- Construction Contract
    Retaining Wall Replacement along a Section of Route 116 (Ashfield Road) and the South River. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/22/2011
    Project Initiation Form PIF Entered 12/22/2011
    Project Initiation Form PRC Submitted 12/22/2011
    Project Review Committee PRC Approved 10/04/1995
    Project Status Advertised 09/07/2013
    Project Management
    25% Design 25% Package Received 11/28/2012
    25% Design 25% Package Comments to DE 12/13/2012
    25% Design 25% Package Comments to DE 02/26/2013
    25% Design Design Public Hearing 01/16/2013
    75% Design 75% Package Received 06/07/2013
    75% Design 75% Package Comments to DE 07/01/2013
    Final Design PS&E Received 07/26/2013
    Final Design PS&E Received 08/29/2013
    Final Design PS&E to FAPRO 09/04/2013