PITTSFIELD- BRIDGE REPLACEMENT, P-10-010, WOODLAWN AVENUE OVER CSX RR
The purpose of this project is to replace the bridge that carries Woodlawn Ave over the CSX RR in Pittsfield.
Location:
  • City of Pittsfield
  • Resident Engineer: Peter Lamarre
    Construction Contract Value: $4,914,591.00
    Construction Bid Price: $4,467,083.00
    Initial Construction Estimate: $4,165,153.50
    District: District 1

    Contracts (5) Progress
    # 55040 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 68384 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 82414 -- Construction Contract
    Bridge Replacement (P-10-010) (Steel) Woodlawn Avenue over CSX Railroad. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/15/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/28/2011
    Project Initiation Form PIF Entered 01/05/2013
    Project Initiation Form PRC Submitted 01/17/2012
    Project Review Committee PRC Approved 02/12/2009
    Project Status Advertised 05/17/2014
    Project Management
    25% Design 25% Package Received 09/10/2012
    25% Design 25% Package Comments to DE 10/11/2012
    25% Design 25% Package Comments to DE 07/16/2013
    25% Design Design Public Hearing 11/28/2012
    75% Design 75% Package Received 03/28/2013
    75% Design 75% Package Comments to DE 05/09/2013
    Final Design PS&E Received 06/10/2013
    Final Design PS&E Received 08/27/2013
    Final Design PS&E Received 03/19/2014
    Final Design PS&E to FAPRO 05/16/2014
    Consultant Contract Process Scope to DE 02/17/2012
    Consultant Contract Process NTP Issued 03/06/2012
    Consultant Contract Process Workhours Approved 02/25/2012