DENNIS- CORRIDOR AND STREETSCAPE IMPROVEMENTS ON MAIN STREET (ROUTE 28), FROM DENNIS COMMONS DRIVE TO UPPER COUNTY ROAD
This project is intended to improve multi-modal accommodation through the reconstruction of sidewalks to ADA specification, providing wider, bicycle accommodating shoulders and streetscape elements including new plantings and street lighting.
Location:
  • Town of Dennis
  • Construction Begins: Spring 2018
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $5,129,121.80
    District: District 5

    Contracts (2) Progress
    # 102131 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Flashing Beacon) along a Section of Main Street (Route 28). Completed
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/30/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/03/2012
    Project Initiation Form PIF Entered 04/26/2012
    Project Initiation Form PRC Submitted 07/13/2012
    Project Review Committee PRC Approved 07/26/2012
    Project Status Advertised 09/02/2017
    Project Management
    100% Design 100% Package Received 12/01/2016
    100% Design 100% Package Comments to DE 02/01/2017
    25% Design 25% Package Received 03/23/2015
    25% Design 25% Package Comments to DE 07/28/2015
    25% Design Design Public Hearing 11/05/2015
    75% Design 75% Package Received 03/04/2016
    75% Design 75% Package Comments to DE 05/10/2016
    Final Design PS&E Received 06/16/2017
    Final Design PS&E to Peer Reviewer 02/15/2017
    Final Design Peer Review Comments to DE 03/16/2017
    Final Design PS&E Received - Resub 1 07/14/2017
    Final Design PS&E Received - Resub 2 08/18/2017