Project Description:
NEW BEDFORD- CORRIDOR IMPROVEMENTS AND RELATED WORK ON KINGS HIGHWAY, FROM CHURCH STREET TO THE KINGS HIGHWAY BRIDGE (N-06-036) OVER ROUTE 140
This project is proposed to address ongoing safety and congestion issues due to the lack of roadway capacity and left turn lanes at several key inter-sections. Traffic signal improvements are also planned at 4 intersections. In addition, the project will provide improved bicycle and pedestrian access.
Location:
  • City of New Bedford
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Nuno Redondo
    Construction Bid Price: $7,891,570.00
    District: District 5
    Current Status: Verizon continues transferring wires from old poles to the new poles. Signal pre-emption coordination is ongoing. Scheduled work hours are Monday through Friday, 7:00 AM to 3:00 PM. Expect periodic lane closures and restrictions. (as of 03/20/2024)

    Contracts (1) Progress
    # 109552 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Kings Highway 75% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 02/05/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Verizon continues transferring wires from old poles to the new poles. Signal pre-emption coordination is ongoing. Scheduled work hours are Monday through Friday, 7:00 AM to 3:00 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/05/2012
    Project Initiation Form PIF Entered 01/06/2012
    Project Initiation Form PRC Submitted 10/30/2012
    Project Review Committee PRC Approved 11/15/2012
    Project Status Advertised 08/31/2019
    Project Management
    100% Design 100% Package Received 03/04/2019
    100% Design 100% Package Comments to DE 04/15/2019
    25% Design 25% Package Received 04/01/2016
    25% Design 25% Package Comments to DE 08/30/2016
    25% Design 25% Package Received - Resub 1 07/01/2016
    25% Design Design Public Hearing 09/26/2017
    75% Design 75% Package Received - Resub 1 04/24/2018
    Final Design PS&E Received 07/09/2019
    Final Design PS&E to FAPRO 08/19/2019