Project Description:
NORTHAMPTON- MAAB/ADA UPGRADES TO THE ADMINISTRATION BUILDING BATHROOMS & FRONT ENTRANCE
This project is to upgrade the existing first floor bathrooms and front entrance to make MAAB/ADA compliant with an Action issued by the MAAB.
Location:
  • City of Northampton
  • Resident Engineer: Gary Sedelow
    Construction Contract Value: $283,582.00
    Construction Bid Price: $248,332.00
    Initial Construction Estimate: $235,000.00
    District: District 2

    Contracts (1) Progress
    # 72917 -- Construction Contract
    MAAB/ADA Uprgrades to the Front Steps and Bathrooms at the MassDOT District 2 Administration Building. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/12/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 01/09/2012
    Project Need Form PNF Entered 01/09/2012
    Project Need Form PNF Approved 01/09/2012
    Project Need Form PNF Denied 01/09/2012
    Project Initiation Form PIF Received 01/09/2012
    Project Initiation Form PIF Entered 01/09/2012
    Project Initiation Form PRC Submitted 01/09/2012
    Project Review Committee PRC Approved 01/10/2012
    Project Status Approved 25% 02/01/2012
    Project Status Advertised 02/25/2012
    Project Management
    100% Design 100% Package Received 02/13/2012
    25% Design 25% Package Received 01/25/2012
    25% Design 25% Package Comments to DE 01/27/2012
    25% Design 25% Package Approved 01/31/2012
    25% Design 25% Plans Complete 01/31/2012
    Final Design PS&E Received 02/17/2012
    Final Design PS&E to FAPRO 02/24/2012