Project Description:
FRAMINGHAM- BRIDGE REPAIR, F-07-003 & F-07-065, WINTER STREET OVER SUDBURY RIVER
(Replaced #602464) The proposed project involves the repair of the existing double barrel arch bridge and the single span bridge carrying Winter Street over the Sudbury River in Framingham. The existing bridge width will remain the same. The horizontal and vertical alignments will remain essentially the same. The bridges will be closed to vehicular traffic during construction. Pedestrian traffic will be maintained during construction by the use of the existing adjacent pedestrian bridge.
Location:
  • Town of Framingham
  • Resident Engineer: Michael Sholock
    Construction Contract Value: $734,950.00
    Construction Bid Price: $612,130.50
    Initial Construction Estimate: $749,380.00
    District: District 3

    Contracts (4) Progress
    # 41489 -- Design -- Geotechnical
    Statewide - implement geophysical methods on statewide designed and constructed bridge and highway projects. Final
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75231 -- Construction Contract
    Bridge Repair (F-07-003) (Concrete) and (F-07-065) (Stone Arch Masonry) both on Winter Street over the Sudbury River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/30/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/11/2012
    Project Initiation Form PIF Entered 01/11/2012
    Project Initiation Form PRC Submitted 01/11/2012
    Project Review Committee PRC Approved 01/11/2012
    Project Status Advertised 08/25/2012
    Project Management
    75% Design 75% Package Received 03/09/2012
    75% Design 75% Package Comments to DE 05/15/2012
    Final Design PS&E Received 08/16/2012
    Final Design PS&E to FAPRO 08/22/2012