LAKEVILLE- RECONSTRUCTION AND RELATED WORK ON RHODE ISLAND ROAD (ROUTE 79), FROM THE TAUNTON CITY LINE TO CLEAR POND ROAD
Work on this project consists of corridor improvements along Route 79 including bicycle lanes, a sidewalk, drainage upgrades and intersection improvements - specifically at the Route 79/Route 18 intersection and the Route 79/Precinct Street intersection. The roadway will be milled and overlaid with box cut widening proposed.
Location:
  • Town of Lakeville
  • Design Responsibility: Municipality
    Construction Begins: Autumn 2025
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $17,156,800.20
    Estimated Total Federal Participating Construction Cost: $18,667,142.23
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 100% Package Received (as of 12/15/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: LAKEVILLE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $18,667,142- $13,253,671 STBG/$5,413,471 CMAQ; d) EC Score 61 of 100; h) Project Proponent - Lakeville; i) Status 100%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $4,330,776.80
    State Cost: $1,082,694.20
    Total Cost: $5,413,471.00

    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: LAKEVILLE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $18,667,142- $13,253,671 STBG/$5,413,471 CMAQ; d) EC Score 61 of 100; h) Project Proponent - Lakeville; i) Status 100%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $10,602,936.80
    State Cost: $2,650,734.20
    Total Cost: $13,253,671.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/24/2012
    Project Initiation Form PIF Entered 01/31/2012
    Project Initiation Form PRC Submitted 01/31/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Management
    100% Design 100% Package Received 12/15/2023
    25% Design 25% Package Received 10/06/2017
    25% Design 25% Package Comments to DE 04/11/2018
    25% Design 25% Package Approved 02/24/2021
    25% Design Design Public Hearing 04/13/2021
    75% Design 75% Package Received 04/22/2022
    75% Design 75% Package Comments to DE 07/25/2022