| Project Description: |
LAKEVILLE- RECONSTRUCTION AND RELATED WORK ON RHODE ISLAND ROAD (ROUTE 79), FROM THE TAUNTON CITY LINE TO CLEAR POND ROAD
Work on this project consists of corridor improvements along Route 79 including bicycle lanes, a sidewalk, drainage upgrades and intersection improvements - specifically at the Route 79/Route 18 intersection and the Route 79/Precinct Street intersection. The roadway will be milled and overlaid with box cut widening proposed.
|
| Location: |
|
| Construction Begins: | Autumn 2025 |
| Resident Engineer: | Alfredo Nunez![]() |
| Construction Bid Price: | $17,385,000.00 |
| District: | District 5 |
| Current Status: | • Environmental walk was done on 4/8/26. • Advanced warning signs were installed on 4/9/26. • Clearing and tree removal started on 4/20/26. • Installation of erosion control began 5/12/26, now complete. • Saw cutting for drainage was completed on 5/21/26. • Drainage construction started on 5/26/26 and is ongoing. • Invasive species spraying was done on 10/1/26. • Tree removal was completed on 10/2/26. • Grubbing shoulders ended on 10/23/26. • Milling and reclaiming (pulverizing) operations finished on 10/27/26. • Box widening and fine grading of the roadway started on 10/28/26. • HMA Base and Binder placement is scheduled to start on 11/12/26. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM (as of 11/09/2026) |
|
Bridges |
||||||||
|
||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||