Project Description:
FALL RIVER- MULTI-USE PATH CONSTRUCTION, FROM BRAYTON AVENUE TO QUEQUECHAN STREET, INCLUDES REHAB OF F-02-106 & F-02-107 (QUEQUECHAN RAILTRAIL - PHASE III)
The proposed project will construct a shared-use trail for pedestrians and bicycles within an abandoned MassDOT owned railroad layout along the scenic Quequechan River, extending from the existing trail at Brayton Avenue to Quequechan Street. The proposed trail will consist of a 10 foot wide paved surface with 2 to 3 foot soft surface shoulders. The project will include new and replacement bridges, intersection improvements, landscaping, and user amenities. This project is Phase II of a multi-phase bike route connecting the existing path at South Watuppa Pond to Britland Park.
Location:
  • City of Fall River
  • Resident Engineer: Francis Grenon
    Construction Contract Value: $1,951,791.00
    Construction Bid Price: $1,752,082.90
    Initial Construction Estimate: $1,424,961.00
    District: District 5

    Contracts (3) Progress
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84271 -- Construction Contract
    Construction of the Quequechan River Rail Trail (Phase 3) (Including 2 Bridges and Signals). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/29/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/31/2012
    Project Initiation Form PIF Entered 03/13/2012
    Project Initiation Form PRC Submitted 03/13/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 08/09/2014
    Project Management
    100% Design 100% Package Received 10/25/2013
    100% Design 100% Package Comments to DE 12/10/2013
    25% Design 25% Package Received 08/02/2012
    25% Design 25% Package Comments to DE 05/30/2013
    25% Design 25% Package Comments to DE 11/13/2013
    25% Design Design Public Hearing 06/26/2013
    75% Design 75% Package Received 10/25/2013
    75% Design 75% Package Comments to DE 12/10/2013
    Final Design PS&E Received 03/24/2014
    Final Design PS&E Received 06/13/2014
    Final Design PS&E to Peer Reviewer 04/24/2014
    Final Design Peer Review Comments to DE 05/07/2014
    Final Design PS&E to FAPRO 08/05/2014