BOXFORD- RECONSTRUCTION ON ROUTE 133 (WASHINGTON STREET) FROM THE NORTH ANDOVER TL TO MAIN STREET
The project will reconstruct Route 133 (Washington Street) from the North Andover town line to Main Street, approximately 1.45 miles. The project will widen the existing pavement width to 30 feet to include two 11-foot lanes and two four-foot shared bicycle/pedestrian lanes and reconfigure three intersections to “T” type intersections. These are Washington Street at Main Street, at Essex Road and at Lakeshore Road. The project will also replace substandard and damaged guardrail, add new guardrail where needed, add sidewalks in the Village District area, add an overhead flashing warning beacon at Main Street, upgrade the existing drainage system to deep sump catch basins, upgrade and extend a 48” culvert and headwalls with an open bottom and stepped culvert.
Location:
  • Town of Boxford
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $4,717,700.70
    Estimated Total Federal Participating Construction Cost: $5,172,164.40
    District: District 4
    Current Status: 25% Package Received (as of 09/18/2015 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2012
    Project Initiation Form PIF Entered 02/13/2012
    Project Initiation Form PRC Submitted 02/29/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Management