Project Description: |
HOLDEN- BRIDGE REPLACEMENT, H-18-008, ROUTE 31 (WACHUSETT STREET) OVER THE QUINAPOXET RIVER
The existing bridge will be replaced with a new single span bridge, along with new roadway approaches, guardrail, sidewalk and slope treatment. The bridge will be open during the proposed staged construction.
|
Location: |
|
Resident Engineer: | Byron Beauregard |
Construction Contract Value: | $2,480,278.00 |
Construction Bid Price: | $1,980,241.88 |
Initial Construction Estimate: | $2,571,035.30 |
District: | District 3 |
|