Project Description:
HOLDEN- BRIDGE REPLACEMENT, H-18-008, ROUTE 31 (WACHUSETT STREET) OVER THE QUINAPOXET RIVER
The existing bridge will be replaced with a new single span bridge, along with new roadway approaches, guardrail, sidewalk and slope treatment. The bridge will be open during the proposed staged construction.
Location:
  • Town of Holden
  • Resident Engineer: Byron Beauregard
    Construction Contract Value: $2,480,278.00
    Construction Bid Price: $1,980,241.88
    Initial Construction Estimate: $2,571,035.30
    District: District 3

    Contracts (4) Progress
    # 54369 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of design assistance in preparing plans, specification and estimate for bridge maintenance, rehabilitation, betterment, and replacement. Final
    # 59044 -- Design -- Bridge Open End
    Work will consist of statewide bridge design for the Accelerated Bridge Program on an open end basis Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79517 -- Construction Contract
    Bridge Repalcement (H-18-008) (Precast NEXT D Beams) - Route 31 (Wachusett Street) over the Quinipoxet. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/24/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/16/2012
    Project Initiation Form PIF Entered 02/16/2012
    Project Initiation Form PRC Submitted 02/16/2012
    Project Review Committee PRC Approved 02/21/2012
    Project Status Advertised 08/31/2013
    Project Management
    25% Design 25% Package Received 04/19/2012
    25% Design 25% Package Comments to DE 05/21/2012
    25% Design 25% Package Approved 06/27/2012
    25% Design Design Public Hearing 08/30/2012
    75% Design 75% Package Received 12/03/2012
    75% Design 75% Package Comments to DE 03/15/2013
    Final Design PS&E Received 07/19/2013
    Final Design PS&E to FAPRO 08/28/2013