Project Description:
DISTRICT 3- CONCRETE COATING APPLICATION TO I-190 (NB & SB) STRUCTURES @ EXIT 1
Application of an elastomeric paint to newly repaired concrete surfaces at I-190 NB and SB (Exit 1).
Location:
Resident Engineer: Patrick Hanley
Construction Contract Value: $325,000.00
Construction Bid Price: $220,125.00
Initial Construction Estimate: $325,000.00
District: District 3

Contracts (1) Progress
# 75353 -- Construction Contract
Concrete Coating Applications at Various Locations. Completed

Bridges

Contract Dates
Notice to Proceed: 01/16/2013
Contract Information
Project Designer: In-House Boston
Funding Source: BRR OFF SYSTEM
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 02/17/2012
Project Initiation Form PIF Entered 02/17/2012
Project Initiation Form PRC Submitted 02/29/2012
Project Review Committee PRC Approved 03/22/2012
Project Status Advertised 09/01/2012
Project Management
Final Design PS&E Received 06/01/2012
Final Design PS&E to FAPRO 06/27/2012