Planned Federal FY: |
2027 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
BOSTON
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
$15,000,000 funded through Boston Region MPO's Regional Target in FFY27 using NHPP. Total Adj. TFPC: $112,056,000
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$8,381,764.00 |
State Cost: |
$2,095,441.00 |
Total Cost: |
$10,477,205.00 |
|
|
|
Planned Federal FY: |
2028 |
Responsible MPO: |
Boston Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
BOSTON
|
Category: |
Advertised Projects Constr. |
Budget Section: |
2A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
$15,000,000 funded through Boston Region MPO's Regional Target in FFY27 using NHPP. Total Adj. TFPC: $112,056,000
|
|
Category |
FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge |
|
Federal Cost: |
$32,060,780.00 |
State Cost: |
$8,015,195.00 |
Total Cost: |
$40,075,975.00 |
|
|
|
|