Project Description:
TAUNTON- RECONSTRUCTION ON COUNTY STREET (ROUTE 140), FROM THE ROUTE 24 (SB OFF-RAMP) NORTHERLY TO MOZZONE BOULEVARD
This project is proposed to address safety issues along County Street (Route 140) from the Route 24 SB off-ramp Northerly to Mozzone Boulevard. The existing roadway is striped as a two-lane bi-directional roadway that effectively operates as a four-lane cross section, thereby compromising safety for pedestrians, bicyclists and motorists. The intent of the project is to eliminate the bottleneck where the roadway narrows at the railroad tracks between the Route 24 SB off-ramp northerly to Mozzone Boulevard.
Location:
  • City of Taunton
  • Resident Engineer: Amy Aveiro
    Construction Bid Price: $2,269,070.32
    District: District 5

    Contracts (2) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90710 -- Construction Contract
    Roadway Reconstruction (Including Signals) along a Section of Route 140 (County Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/06/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2012
    Project Initiation Form PIF Entered 02/24/2012
    Project Initiation Form PRC Submitted 02/24/2012
    Project Review Committee PRC Approved 03/22/2012
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 01/23/2015
    100% Design 100% Package Comments to DE 03/23/2015
    25% Design 25% Package Received 01/10/2014
    25% Design 25% Package Comments to DE 04/08/2014
    25% Design Design Public Hearing 06/03/2014
    75% Design 75% Package Received 01/23/2015
    75% Design 75% Package Comments to DE 03/23/2015
    Final Design PS&E Received 07/31/2015
    Final Design Peer Review Comments to DE 08/18/2015
    Final Design PS&E to FAPRO 09/08/2015